PMBOK® Guide defines 3 different types of Fixed Price (FP) Contract. I have written about Firm Fixed Priced Contract (FFP) and Fixed Price with Economic Price Adjustment Contract (FP-EPA) in other posts. In this post, I will talk about Fixed Price Incentive Fee (FPIF) Contract.
You should also read the formal explanation and example of different Contracts before reading this article.
The basic nature of FPIF Contract is very much like a FP Contract but there is some price flexibility built into the contract. The price flexibility is achieved through financial incentive(s). The Buyer and Seller agree upon financial incentive(s) and establish some performance criteria as part of the contract. The Seller is entitled to the agreed upon incentive(s) after meeting or exceeding the established performance criteria.
FPIF Contracts can have provision for negative incentives also. These are often called penalties. The penalties are levied in case the Seller does not meet established performance criteria.
In FPIF Contract, the final price is determined only after completion of the contracted work. The final price can vary based on the performance of the Seller.
In FPIF Contract, the Buyer and the Seller can use any project parameter to establish the performance criteria. Project parameters can include Schedule, Cost, Quality, technical performance etc. Following are some examples of performance criteria.
The defined performance criteria can be based on a single project parameter or on a combination of multiple project parameters. One of the more popular performance criteria is based on cost performance of the Seller. The cost performance is established by defining Cost Targets at the outset. I have written a separate articles on cost related performance targets and Point of Total Assumption. I have explained 6 different FPIF formulas in these articles.
The same general formula that we discussed for FFP contract, is applicable for FPIF Contract also.
Price = Cost + Fee
The formula is explained in my previous article PMP Formulas behind Contract Types. The definitions of Price, Cost and Fee are also explained in the same article.
The Fee calculation can be done only after determining the Incentives as defined in the Contract.
I hope that you were able to understand part of the topic. In the next post, I will talk about cost related incentives and Point of Total Assumption. Meanwhile, if you have any question, please leave a comment.
You can refer to Max Wideman Glossary to read some standard definitions of Fixed Price Incentive Fee Contract.
I hope you were able to understand the formulas behind FPIF Contract. Please leave a comment if you have a doubt.
I have also compiled a PMP Formulas Cheat Sheet. It contains 45 formulas and 57 abbrviations. It will help you in your exam prep. It is the best and most comprehensive cheat sheet based on the PMBOK Guide 6th edition. You can download it free of cost for your studies.
If you are looking beyond a cheat sheet, then I would suggest you to buy detailed PMP Exam Formula Study Guide by Cornelius Fichtner. It contains detailed explanations of all the formulas along with examples and 105 practice questions.
Disclosure: This article contains affiliate links - it means that, if you buy from any of these links, then I will receive a small commission that would help me in maintaining this blog for free. However, for you, there is no extra cost. I recommend only those products that I believe will definitely help the certification aspirants.
Image courtesy of phasinphoto at FreeDigitalPhotos.net